SHERMAN IMMEDIATE CARE FACILITY

Healthcare

AG体育官方网站 Construction Company was contracted to build a 32,000-square-foot, two-story building to accommodate a Sherman Hospital Immediate Care facility on the first floor with offices for a law firm and other professional tenants on the second floor.

CHALLENGE:

The wildly different tenant requirements imposed divergent criteria for heating, ventilating and cooling, structural engineering and building access. The immediate care facility, for example, is open 13 hours a day, while the professional offices are open primarily during traditional business hours.

SOLUTION:

The solution to the access issue was to create separate entrances with adjacent parking convenient to both lobbies. Second-floor tenants have key card entry after hours, while medical staff cannot enter after the facility is locked. The HVAC issues were solved with two separate, low-profile roof units, both controlled by a single computerized building automation system that allows for multiple temperature settings in different zones. On the structural side, the concern was supporting Sherman鈥檚 10,000-pound CT scanner. AG体育官方网站 addressed the issue by pouring a 12-inch slab (five inches is normal) with steel reinforcement under the scanner room.

RESULTS:

The new building successfully accommodates all tenants鈥� needs. The attractive brick veneer exterior with EIFS banding gives the dual-purpose structure a welcoming, non-institutional fa莽ade without sacrificing the professional appearance required for an office building.


Architects:

Ware Malcomb

Square Footage:

32,000

Location:

South Elgin, IL

Related
Projects: